Over the last month, our team has been working with the contractor, our construction management company, and our architect to develop a plan for the project. We are now in a somewhat accelerated period of the work, and the first impact to families will occur next week as outlined below.
On Monday, Door S, which has been used for some 3rd, 4th, and 5th grade student arrival and After Care, will no longer be available.
- The area around Door S will become the construction staging area and will contain dumpsters and scaffolding.
- Mr. Tennant has drafted a revised arrival and dismissal letter, which will also be sent in a separate message from the school.
-
After Care pickup will move to Door B in the horseshoe. Please refer to this image for clarification.